Eskbank St Square

The concrete pour of the South lane of the Main St through the intersection has been undertaken. The concrete will require the next week to cure. The new kerb line on the South side of the intersection has been partially constructed, which helps to give a visual of the new layout of the finished intersection.

Cook St Plaza

This week the majority of the brick paving and concrete work in the plaza was completed. The next stage of work will involve demolition and footpath construction in front of the Post Office Boxes at the rear of the plaza.

Main St Raised Pedestrian Crossing

Concrete has been laid on the North side of the raised pedestrian crossing and construction has started on the footpath paving slab in front of the train station entrance. The 4 week one-way period will end Friday 16 March 2018 as scheduled.