Eskbank St Square

Eskbank St remains closed between Main St and Main St lane while work continues on the Southern portion of the intersection. Demolition work in the roadway has been completed and the site is being prepared for kerb and gutter construction and construction of the concrete road over the next week.

 

Cook St Plaza

One way traffic restrictions have commenced on Main Street while work is undertaken on the raised pedestrian crossing adjacent to Cook Plaza and the train station. Over the past week traffic control and the work site have been set-up and demolition has been undertaken on the Southern half of the crossing. Over the next week the base slab will be prepared and the Southern Crossing slab will be poured. The concrete will need time to set prior to traffic being switched to allow construction of the North side of the crossing.

One way traffic restrictions on Main Street will remain in until 16 March 2018 weather permitting.